Sl.No. |
Services |
Time Limit |
Designated Officer |
Appellate Authority |
Revisional Authority |
1 |
Inspection of Boilers and issue of provisional order to operate |
15 days from the date of receipt of the application. |
Zonal Assistant Director, F & B |
Divisional Deputy Director, F& B |
Director F & B |
2 |
Approval of repair order of boilers |
15 days from the date of receipt of the application. |
Section Officer |
Joint Director, F & B |
Director F & B |
3 |
Approval of Drawings of Steam Pipeline |
30 days from the date of receipt of the application. |
Assistant Director, F & B |
Joint Director, F & B |
Director F & B |
4 |
Registration of Boilers |
30 days |
Assistant Director, F & B |
Divisional Deputy Director, F& B |
Director F & B |
5 |
Endorsement of Certificates of Boiler Operation Engineers, Boiler Attendants and Welders issued by other states. |
15 days |
Section Officer |
Secretary of Respective Board (Assistant Director, F&B / Deputy Director, F&B) |
Chairman (Director, F&B) |
6 |
Revalidation of Welder's Certificates |
15 days |
Section Officer |
Deputy Director, F&B |
Director F & B |
7 |
Grant of Certificate for Manufacture of Boilers and pressure part components under the Boilers Act 1926 |
15 days |
Deputy Director of Factories and Boilers |
Joint Director of Factories and Boilers |
Director of Factories and Boilers. |
8 |
Renewal Certificate for manufacture of Boilers and pressure part components under the Boilers Act, 1923 |
7 days |
Deputy Director of Factories and Boilers |
Joint Director of Factories and Boilers |
Director of Factories and Boilers. |
9 |
Grant of Erector Certificate for Boiler and Steam pipeline under the Boilers Act, 1923 |
15 days |
Deputy Director of Factories and Boilers |
Joint Director of Factories and Boilers |
Director of Factories and Boilers. |
10 |
Renewal of Erector Certificate for Boiler and Steam pipeline under the Boilers Act, 1923 |
7 days |
Deputy Director of Factories and Boilers |
Joint Director of Factories and Boilers |
Director of Factories and Boilers. |
11 |
Grant of Repair Certificate for Builders and Steam pipeline under the Boilers Act, 1923 |
15 days |
Deputy Director of Factories and Boilers |
Joint Director of Factories and Boilers |
Director of Factories and Boilers. |
12 |
Renewal of repair for Boilers and Steam pipeline under the Boilers Act, 1923 |
7 days |
Deputy Director of Factories and Boilers |
Joint Director of Factories and Boilers |
Director of Factories and Boilers. |
13 |
Disposal of application for registration under Odisha Shop and Commercial Establishment Act, 1956 |
15 days |
District Labour Officer / Assistant Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
14 |
Disposal of application under the Motor Transport Workers Act, 1961 for Registration or Renewal (Annual) |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
15 |
Disposal of application under the Beedi & Cigar Workers Act, 1966 for License and for Renewal (Annual) |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
16 |
Disposal of application under the Contract Labour (R&A) Act, 1970 for Registration (one time), for License and for Renewal (Annual) |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
17 |
Disposal of application under the Inter State Migrant Workmen Act, 1979 for Registration (one time), for License and for Renewal of License |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
18 |
Disposal of application under the Building & Other Construction Workers (RE&CS) Act, 1996 for Registration of Establishment |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
19 |
Disposal of application under the Industrial Employment Standing Order Act, 1946 |
60 days |
Divisional Labour Commissioner |
Joint Labour Commissioner |
Labour Commissioner |
20 |
Disposal of application for approval of factory plans (Non-hazardous factories) |
30 days |
Assistant Director, F&B |
Joint Director, F&B |
Director, F&B |
21 |
Disposal of application for approval of factory plans (hazardous factories) |
60 days |
Assistant Director, F&B |
Joint Director, F&B |
Director, F&B |
22 |
Disposal of application for approval of factory plans (major Accident hazard factory) |
90 days |
Assistant Director, F&B |
Joint Director, F&B |
Director, F&B |
23 |
Disposal of application for registration and licensing of Factories |
30 days |
Assistant Director, F&B |
Joint Director, F&B |
Director, F&B |
24 |
Disposal of application for renewal / Amendment / Transfer of Factory License |
30 days |
Section Officer |
Joint Director, F&B |
Director, F&B |
25 |
Disposal of application for issue of Duplicate License |
30 days |
Section Officer |
Joint Director, F&B |
Director, F&B |
26 |
Disposal of application under the Trade Union Act, 1926 for Registration and Amendment |
45 days |
Deputy Labour Commissioner |
Joint Labour Commissioner, Hqrs |
Labour Commissioner, Odisha |
27 |
Approval of On-site Emergency Plan under the provisions of the Factories Act, 1948 |
60 days |
Section Officer |
Dy. Director of Factories and Boilers, (Safety) |
Director of Factories and Boilers |
28 |
Acceptance of Safety Officers under the provisions of the Factories Act, 1948 |
60 days |
Section Officer |
Dy. Director of Factories and Boilers, (Safety) |
Director of Factories and Boilers |
29 |
Approval of manufacturing drawing for Boilers under the Boilers Act, 1923 & IBR, 1950 |
15 days |
Section Officer |
Dy. Director of Factories and Boilers, (Safety) |
Director of Factories and Boilers |
30 |
Approval of manufacturing drawing for retrofit under the Boilers Act, 1923 & IBR, 1950 |
15 days |
Section Officer |
Dy. Director of Factories and Boilers, (Safety) |
Director of Factories and Boilers |
31 |
Amendment of Registration Certificate under Rule-10 of the Odisha Shops & Commercial Establishments Rules,1958 |
15 days |
District Labour Officer / Assistant Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
32 |
Amendment of Certification of Registration under Rule-20 of the Odisha Contract Labour (R&A) Rules,1975 |
15 days |
District Labour Officer / Assistant Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
33 |
Amendment License under Rule-28 of the Odisha Contract Labour (R&A) Rules,1975 |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
34 |
Amendment of Certification of Registration under Rule-6 of the Odisha Inter State Migrant Workmen (RE&CS) Rules,1980 |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
35 |
Amendment License Rule-14 of the Odisha Inter State Migrant Workmen (RE&CS) Rules,1980 |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
36 |
Amendment of Certification of Registration Rule-22(3) of the Odisha Building and Other Construction Workers (RE&CS) Rules, 2002 License |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
37 |
Amendment/ Transfer of Certificate of Registration Rule-9 of the Odisha Motor Transport Workers Rules, 1966 |
15 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |
38 |
Approval of the list of National & Festival Holidays Rule-3 of the Odisha Industrial Establishments (National & Festival) Holidays Rules,1972 |
30 days |
District Labour Officer |
Divisional Labour Commissioner |
Joint Labour Commissioner |